Project: College Park woods Pool Facility

Location

3545 Marlbrough Way

Status

Currently the contractor, Broughton Construction, is in the process of working with Prince George’s  County DPIE to close out the demolition and rough grading permitting requirements. The application for construction permit approval is underway to begin reconstruction of the new clubhouse. Anticipate new facility construction to begin in early summer 2021. In mid-January DPIE permitting approved to the start of rough grading of the site to prepare the land for the construction of the new facility.  Additional design and value engineering had to be performed to achieve construction of the new facility within budget. Modifications to the original concept plan and design drawings have been accomplished. New 100% design drawings have been received and uploaded to the project page.  

The contractor, Boughton Construction LLC., is beginning awaiting PG County construction permit approval to begin reconstruction of the new clubhouse. Anticipate new construction to begin Fall 2020

About the Project

The City of College Park purchased the property called the College Park Swim Club July 2018. The City asked Buchart Horn Architects to perform a facility assessment report to determine costs to repair, replace, and upgrade the necessary components of the facility and advise on recommended steps to proceed with the project. On January 22, 2019 staff outlined the recommended steps forward to the Council and received council feedback to decommission the pool by filling it in and consensus to construct a new facility.

Currently the contractor, Boughton Construction LLC., is applying for the PG County construction permit approval to begin reconstruction of the new clubhouse. Anticipate new construction to begin early summer 2021. Completion Fall 2021.

For questions and comments about the project, please email cpwoodsproject@collegeparkmd.gov. 

Funding

Anticipated Total Project Cost: $999,776.

Estimated Construction cost: $999,776. 

Funding comes from the City’s General Fund.  A funding for a State bond bill of $150,000 has been requested.

Estimated Completion Date

Substantial Completion late Fall 2021

CP Woods Pool Facility Aerial Map - Buchart Horn Final Assessment Report July 24 2018

Project Documents

  • Revised Budget
  • Community Meeting - Dec. 19, 2019
  • Community Meeting - Nov. 14, 2019
  • Buchart Horn Final Assessment Report - July 24, 2018
  • College Park Woods Concept Presentation
  • Revised Drawings - January 2021
11/14/19 Community Meeting


Image 1Image 2Image 3Image 4
Image 5Image 6Image 7Image 8 


Bid and RFP Documents

  • RFP-CP-19-05 Demo-Construction CP Woods pool property
  • Section XI PRICE PROPOSAL DESIGN BUILD POOL
  • GENERAL TERMS AND CONDITIONS 2019 Pool
  • Exhibit A Site Assessment and Plan
  • Design Build contract draft
  • County regulations - to fill in pools
  • 076-01-CPWSC ALTA survey Pool 2
  • RFP.CP-19-05 Design Build Questions
  • Cp-19-05 Pre Bid Meeting Sign In Sheet

Contacts

Project Manager

Robert Marsili Jr., Director

Department of Public Works




Media Inquiries

City Communications

Homepage
Notify me
facebook
Twitter
Insgram
  1. City Hall
    7401 Baltimore Avenue
    College Park, MD 20740
    Departments & Hours

  2. Phone:
    240.487.3500
Site Map
Report a Problem
Privacy & Accessibility
Careers
Webmaster
Employee Login
  1. COVID-19 Updates & ARPA Assistance
  2. City Departments
  3. City Governance
  4. Guides to College Park
  5. Calendar
  6. Events
  7. News
  8. Maps
  9. Places
  10. Projects
  11. About the City
  12. Store
  13. Pay & Apply
  14. Alerts & Notices
  15. Report
Arrow Left Arrow Right
[]
Slideshow Left Arrow Slideshow Right Arrow