Location
3545 Marlbrough Way
Status
Currently the contractor, Broughton Construction, is in the process of working with Prince George’s County DPIE to close out the demolition and rough grading permitting requirements. The application for construction permit approval is underway to begin reconstruction of the new clubhouse. Anticipate new facility construction to begin in early summer 2021. In mid-January DPIE permitting approved to the start of rough grading of the site to prepare the land for the construction of the new facility. Additional design and value engineering had to be performed to achieve construction of the new facility within budget. Modifications to the original concept plan and design drawings have been accomplished. New 100% design drawings have been received and uploaded to the project page.
The contractor, Boughton Construction LLC., is beginning awaiting PG County construction permit approval to begin reconstruction of the new clubhouse. Anticipate new construction to begin Fall 2020
About the Project
The City of College Park purchased the property called the College Park Swim Club July 2018. The City asked Buchart Horn Architects to perform a facility assessment report to determine costs to repair, replace, and upgrade the necessary components of the facility and advise on recommended steps to proceed with the project. On January 22, 2019 staff outlined the recommended steps forward to the Council and received council feedback to decommission the pool by filling it in and consensus to construct a new facility.
Currently the contractor, Boughton Construction LLC., is applying for the PG County construction permit approval to begin reconstruction of the new clubhouse. Anticipate new construction to begin early summer 2021. Completion Fall 2021.
For questions and comments about the project, please email cpwoodsproject@collegeparkmd.gov.
Funding
Anticipated Total Project Cost: $999,776.
Estimated Construction cost: $999,776.
Funding comes from the City’s General Fund. A funding for a State bond bill of $150,000 has been requested.
Estimated Completion Date
Substantial Completion late Fall 2021