LOCATION
Rhode Island Ave. between Greenbelt Rd. and Muskogee Street
ABOUT THE PROJECT
The project will provide final design plans for protected bike lanes along Rhode Island Avenue between Muskogee Street and Greenbelt Road. The project will provide a safe cycling route that helps connect the Greenbelt Metro Station and the Hollywood commercial district with downtown College Park. This project will build on existing preliminary design plans that were finalized in May 2018.
STATUS
Design plans and specifications 100% complete. Contract for construction will be awarded after road work completed by Prince George's County. Resurfacing completed and striping pending.
Funding
Anticipated Total Design Cost: $140,000
Design funding comes from a Maryland Department of Transportation Bikeways grant.
Estimated Cost for Construction (not currently funded):
Phase 1 - $530,000 University Blvd. to Muskogee St.
Phase 2 - $465,000 Greenbelt Rd. to Univesity Blvd.
*Construction cost estimates include 20% contingency
Estimated Completion Date
Estimated design completion - July 2021